Utility Renovation: Completion, Timeline and Costings
It’s been a labour of love/hatred, with lots of blood, sweat and tears - no joke! - but the utility room and downstairs cloakroom are so almost finally done. Before I finally share the finished room reveal of the bathroom, I wanted to go through all the steps it took to get to this point. It's been a long and lengthy journey but we made it. It was originally suppose to be done in September, then October, then December. I had a few things done prior to the main work but the plumbing finally got started properly in January, expecting to take 2 weeks from start to finish. Well, it took almost a full 3 months in the end with tradesmen stopping and starting, as well as doing some of the work myself and here's what happened along the way.
- August 2022: planning the space
- October 2022: moving the electricity supply outside
- November 2022: new RCD board and LED lights
- January 2023: first fit
- January 2023: building a stud wall and plastering
- February 2023: painting and building units
- February 2023: tiling
- March 2023: new internal doors
- March 2023: cloakroom fit
- March 2023: finishing touches and skirting board
- June 2023: boiler cupboard
- Units from Wren: £1,210
- Electricity: £560
- Moving electrical supply: £1,095
- First fit: £435
- Stud wall (materials and fitting): £0 - it was a Christmas present from my dad and he built it
- Plastering: £400
- Paint and supplies: £73 (I also used leftover paint from painting the house last year)
- Doors (5 doors, with handles, hinges, latches, architrave and bathroom lock, plus fitting): £760
- Tiling and final fit: £200 (I used tiles leftover from the bathroom upstairs)
- Toilet, sink and accessories: £305 (I got these from PlumbWorld myself but going through a tradesman would have probably been cheaper)
- Decorations: £339
- Boiler cupboard: £270
Comments
Post a Comment